Tuesday 4/16/2013


Weather: Snow and WINDY 49˚/21˚ 

Subs on Site
<Wholesale Flooring        (4)
<Wall to Wall>                  (2)
<Nutek>                            (10)
<Diamond Z>                    (3)
<Air Doctors>                    (4)
<Warburtons>                  (8)
<Extreme Fire>                 (1)
<Reliance>                       (3)
<Red Oak>                       (6)
<DG Concrete)                 (3)

Work in Progress
(Wholesale Flooring) Installed Vinyl in Building 'E'.

(Wall to Wall) Stripped and Hung doors in 3rd & 4th floor Building 'E'.  Started Touch up in Building 'C'.

(Nutek)  Taped on 2nd floor Building 'B'. Hung 2nd and 2 units on the 3rd floor North Tower of Building 'B'.  Started touch-up in Building 'C'.

(Diamond Z) Continued the stone on the East Columns and South end of Building 'B'.

(Air Doctors) Ran the flues for the water heaters and furnaces on Building 'C'.  Started Stocking furnaces in Building 'D'.  Borrowed the siding guys lift and installed the dryer vent flappers on Buildings 'C' and 'D'.

(Warburtons) Siding in the corridors of Building 'B'. 

(Extreme Fire) Fixed the broken sidewall head in Building 'B' and finished the FDC.  We turned on the water to Building 'E' and only two of the heads had poped.

(Reliance) Trim on Building 'E'.  Installed the fire panel in Building 'C'.

(Red Oak) Started to cut lines in Building 'B' North corridors and patios but it was still too green.  They cleaned up their trash piles on site. 

(DG Concrete) Based the sidewalks down to in front of Building 'D'.  Finished all they could around Building 'C' without blocking access to the North Side.  They also install drains in the window wells around Building 'C' so that the run off from the roof would not fill them.