Tuesday 4/2/2013

Weather: Rain 60˚/33˚ 

Subs on Site
<Sterns>                          (6)
<Wall to Wall>                  (1)
<SBS>                              (3)
<Nutek>                            (6)
<Warburtons>                  (8)
<Air Doctors>                   (3)
<Reliance>                       (3)
<Utek>                              (3)

Work in Progress
(Sterns) Poured the corridors in Building 'E'

(Wall to Wall) Painted the inside of the door frames and the punch list items  on Building 'A'

(Nutek) Taped the corridors in Building 'A' & 'C'.  Pre rocked the 2nd and 3rd floor North Tower in Building 'B'

(Warburtons) Siding in the corridors of Building 'B'.  And the entry gables on the North side of Building 'D'.

(Air Doctors) Trim for Building 'C'.  Started the hard ducts for the North Tower Building 'B'

(Reliance) Started on the corridors of Building 'C today. 

(Utek) Arrived at 2 pm and started on drops on 1st floor in Building 'B'