Subs on Site
<Clegg Steel> (2)

<Air Doctors> (4)
<Reliance> (5)
<Utek> (19)
<Red Oak> (4)
Work in Progress:
(Clegg Steel) welded the steel pans on each of the stairwell flat spots. They started cutting the base plates down for the columns but ran out of daylight. They also did not bring the embeds for the dumpster gates.

(Extreme Fire) finished Building 'A' second floor fire sprinklers
(Air Doctors) worked on the vents for Building 'A'
(Reliance) worked on setting boxes and drilling holes on Building 'A' first floor and fixed the conduits that Shad (DG Concrete) hit with his loader.
(Utek)Set the remainder of the trusses on Building 'A' and started sheeting the middle section. Finished Building 'E' lower walls. Sheeted Building 'C' second floor breeze way floors and started rolling Building 'D' 2nd floor. Started Building 'C' 2nd floor walls. Continued pre-fab.
(Red Oak) formed the patios on Building 'A'