Tuesday 10/16/2012


Weather:Partly Cloudy  67˚/38

Subs on Site
<Star Paving>                (8)
<Air Doctors>               (3)
<Utek>                          (10)
<DG Concrete>             (2)

Work in Progress:
(Star Paving) Paved all of Building 'A' lot

(Air Doctors) Finished all their pre-rock work on both ends of Building 'A'

(Utek) Finished Building 'B' garage and started layout for prefab of Building 'C' floor.

(DG Concrete) laid the last sleeve for Questar and finished E-fill and 75% of the Road base between Building 'C' & 'B' garages.