Tuesday 10/23/2012



Weather: Cloudy & Windy 58˚/37˚

Subs on Site
<Extreme Fire>             (3)
<Nutek>                        (6)
<Questar>                    (5)
<Utek>                          (18)

<Red Oak Plumbing      (2)
<Red Oak>                    (7)
<DG Concrete>             (2)


Work in Progress:
(Extreme Fire) arrived on site at 3 pm and started install.

(Nutek) hung drywall in the shafts for HVAC and  Plumbing pipes.

(Questar) ran the services to Building 'C'.  Building 'A' service needed to be a larger sleeve than Ian (B.Jackson) asked for so they had to missile it.  The missile did not work so they had to boor it.

(Utek)set the Pre-fabbed sections of trusses on Building 'A', worked on interior pick-up in Building 'A'  and continued on Building 'E' 1st floor walls.  Pre-fabbed walls for Building 'D'

(Red Oak Plumbing) started rough-in on Building 'A'

(Red Oak) Poured the ends of Building 'B' and passed inspection on the center section.

(DG Concrete) graded dumpster pads.


Sub Meeting:
William (Air Doctors)
Pablo (Extreme Fire)
Konrad (Nutek)

We decided that we would be running the heat vent in the master closet of the 3x2 units out the wall instead of from the ceiling.  That way we would not have to drop the ceiling.