Subs on Site
<Extreme Fire> (3)
<Air Doctors> (4)
<Utek> (18)
<Reliance> (3)
<Red Oak Plumbing (2)
<Red Oak> (7)
Work in Progress:

(Air Doctors) Started running the Flue Vents on the South end of Building 'A'
(Utek) Started pre-fabing the rest of the center section's trusses. The snow was bad enough that they had to leave for a longer lunch. They did return for a couple hours in the afternoon. The pre-fab yard continued on with wall panels.
(Reliance) set the panels in the units on Building 'A'
(Red Oak Plumbing) drilled all of the holes for plumbing on the North end of Building 'A'
(Red Oak) poured the center section of Building 'B' at 5 AM. The rain/snow started at 8;30. They went a picked up some plastic and returned after lunch. They finished when the rain/snow would let up enough. I called Dennis (Sterns) and asked if we could rent some Concrete blankets because the low is suppose to be in the low 20's