Subs on Site
<Extreme Fire> (3)
<Air Doctors> (4)
<Reliance> (3)
<Utek> (20)
<Red Oak Plumbing (6)
<Red Oak> (7)
Work in Progress:

(Air Doctors)Installed the flue vents on the middle section of Building 'A'
(Reliance) Installed the panel on the North end of Building 'A'. Rulon came up to go over layout and circuits with Bryson.

(Utek) craned up the rest of the middle section trusses and started pre-fab of the South end of Building 'A', Sheeted Building 'C' 2nd floor. Built interiors on Building 'E', and continued pre-fab of wall sections.
(Red Oak Plumbing) finished the drain plumbing on Building 'A' first floor and drilled holes for the gas lines.
(Red Oak) poured the Breeze ways and patios for Building 'B'.

(Red Oak) poured the breeze ways and patios on Building 'B' they planned on pouring at 8 AM but there was frost last night so the moved it to 10 AM and it melted.