Wednesday 10/10/2012


Weather: Sunny  72˚/43˚

Subs on Site
<Star Paving>                (8)
<Air Doctors>               (3)
<Utek>                          (14)
<DG Concrete>             (2)

Work in Progress:
(Star Paving) Started finial grade on the road from the intersection to t

(Sterns) formed and poured the waterway between Building 'C' and 'B's garages.

(Air Doctors) Drilled and installed the exhaust fans and cold air returns on the South end, bottom 2 floors (4 units)

(Utek)Built the center units on Building 'C'.  Rolled trusses on the Building 'A' garage and sheeted the North side.

(DC Concrete)Installed the E-fill and then road base North of the intersection and E-fill in Building 'B' parking lot and passed inspection on all.