Weather: Sunny 72˚/43˚
Subs on Site
<Star Paving> (8)
<Air Doctors> (3)
<Utek> (14)
<DG Concrete> (2)
Work in Progress:
(Star Paving) Started finial grade on the road from the intersection to t
(Sterns) formed and poured the waterway between Building 'C' and 'B's garages.(Air Doctors) Drilled and installed the exhaust fans and cold air returns on the South end, bottom 2 floors (4 units)
(Utek)Built the center units on Building 'C'. Rolled trusses on the Building 'A' garage and sheeted the North side.
(DC Concrete)Installed the E-fill and then road base North of the intersection and E-fill in Building 'B' parking lot and passed inspection on all.