Monday 10/29/2012

Weather: Sunny 59˚/36˚

Subs on Site
<Extreme Fire>             (3)
<Air Doctors>                (4)
<Reliance>                    (5)
<Utek>                          (19)
<Red Oak Plumbing      (2)

Work in Progress:
(Extreme Fire) Tested the 1st floor fire sprinklers


(Air Doctor) stared on more vents for Building 'A" but we may have a problem with using PVC 

(Reliance) boxed out the 1st floor units and started drilling holes

(Utek) set up to 80% of the trusses on Building 'A', sheeted Building 'C' 2nd floor,  Built interiors on Building 'E' 1st floor and continued pre-fab of the wall units.



(Red Oak Plumbing) ran vent pipes on Building 'A' 2nd floor.