Thursday 10/25/2012

Weather: Snow 41˚/29˚

Subs on Site
<Extreme Fire>             (3)
<Air Doctors>                (4)
<Reliance>                    (3)
<Utek>                          (20)
<Red Oak Plumbing      (6)
<Red Oak>                    (7)

Work in Progress:
(Extreme Fire)continued fire sprinkler install in Building 'A' 1st floor.

(Air Doctors) Finished the vents in the Southern end units and started in the middle units.

(Reliance) Set the exterior power panels.

(Utek)framed Building 'E' 1st floor, started sheeting Building 'C' 2nd Floor, Pre-fabbed more truss sections for Building 'A', and continued pre-fab of walls.

(Red Oak Plumbing) installed the drain pipe for the Northern half of Building 'A'

 (Red Oak) formed Building 'B' breeze ways and patios.