Subs on Site
<Star Paving> (8)
<Utek> (14)
Work in Progress:
(Star Paving) passed compaction on the main road from the intersection to 2500 W then down the west parking lot for Building 'A'. The rain made it too wet to work by 8:00 AM. They tried to start again at 11:00 AM and were rained out in less than an hour.
(Utek) Sheeted Building 'C' garage and framed the East end of Building 'C' walls.