Subs on Site
<Star Paving> (8)
<Utek> (18)
Work in Progress:
(Star Paving) Fixed their paver and paved from the intersection East and South to finish the site. They will come back and patch the crane hole when they pave in Ballard.
(Utek) Finished framing the 1st floor on Building 'D' and set the pre-fabbed floor sections for the 2nd floor on Building 'C'. As well as continuing pre-fab on Building 'C' walls.