Thursday 10/11/2012


Weather:Partly Cloudy  71˚/46˚

Subs on Site
<Star Paving>                (8)
<Air Doctors>               (3)
<Utek>                          (14)
<DG Concrete>             (2)

Work in Progress:
(Star Paving) Graded and rolled the the main road from the intersection to 2500 W then down the west parking lot for Building 'A'.  They pass compaction on the lot in front of Building 'E'.

(Air Doctors)Continued up the the Southern end of Building 'A' with exhaust fans and cold air returns on 3 units for a total of 7 complete.

(Utek)Jess Finished the center section and started the West end of Building 'C' 1st floor.  Alma Finished sheeting Building 'A' garage and set trusses on Building 'C' garage.

(DG Concrete) Fixed the valve boxes and set them to road elevation, put road base in Building 'B' parking lot and sand in the lot between the garages.