Subs on Site
<Clegg Steel> (4)
<Star Paving> (8)
<Air Doctors> (3)

<Utek> (15)
<DG Concrete> (2)
Work in Progress:
(Clegg Steel) installed the rest of the stairs on Building A and the first gable of structural steel. The peak beam was too short(to the column instead of to the building). The base plates on the structural steel were too big(16"x24" instead of 12"x12"). I approved the steel submittal and just missed it.
(Star Paving) Paved Building 'C' lot, the lot between Building 'C' & 'B' garages and the road from 2500 W to between Building 'D' and 'E'.
(Air Doctors)Ran line sets for Building 'A' units
(Utek) started framing Building 'D' walls, pre-fab on Building 'C' 2nd floor and 2nd floor walls.

(DG Concrete) finished the road base in between Building 'C' & 'B' garages and started gravel in Building 'B'
Sub Meeting:
Wayne (Extreme Fire) came to the site. We looked over the Building. He needs to go over the top of the exhaust vent pipes and it will be a tight fit. He said he would start on Monday 10/22 and it would take 1 week per floor.
William (Air Doctors) said they were not planing on installing the furnaces until after paint but if we would like to use them for heat during construction we would have to replace the filter weekly and sign off the warranty.