Thursday 10/18/2012

Weather: Sunny  61˚/31˚

Subs on Site
<Star Paving>                (8)
<Air Doctors>               (3)
<Utek>                          (15)
<DG Concrete>             (2)

Work in Progress:
(Star Paving) Paved Building 'B' lot, to the intersection and North to the end of the road.  They broke a sprocket on their paver at the end of the day.

(Air Doctors) Finished the Line sets for the whole of Building 'A'

(Utek) Finished all exteriors and party walls on Building 'D'.  Finished pre-fab on the 2nd floor and 2nd Floor wall for Building 'C'.  They had to wait for the asphalt to cure before setting their floor sections. Trusses were also delivered today.

(DG Concrete) Graveled both ends of Building 'B' and started in the center.

(Warburtons) Randy and Rick came by for a pre-con  They measured the garages and Building 'A'.  Rick told me that it would be 3 weeks before siding could be delivered.