Weather: Partly Cloudy 31˚/7˚
Subs on Site
<G & M> (5)
<Wall to Wall> (4)
<SBS> (1)
<Nutek> (10)
<Cardalls> (4)
<Warburtons> (8)
<Air Doctors> (4)
<Nutek> (10)
<Cardalls> (4)
<Warburtons> (8)
<Air Doctors> (4)
<Clegg Steel> (6)
<Utek> (12)
<Utek> (12)
<Reliance> (4)
<Red Oak Plumbing> (6)
Work in Progress:
(G & M) Installed cabinets on the North end of 2nd and 3rd floor in Building 'A'.
(Wall to Wall) Painted 8 units on the 4th floor of Building 'A'.
(Wall to Wall) Painted 8 units on the 4th floor of Building 'A'.
(SDS) Hung the Breeze way doors on the East side 3rd and 4th in Building 'C'
(Nutek)Fire taped pre-rock on the East end of 3rd and 4th floor in Building 'C' Taped behind the tubs on Building 'E'. Finished hanging the sheetrock on 1st floor of Building 'C' and started taping it. LKL delivered the sheetrock for Building 'D' and stacked it for speedy stocking in the Building tomorrow. .
(Warburtons) Worked on the West Breezeway 2nd floor of Building 'C'. Installed siding on the South center and West sections of Building 'C'
(Air Doctors) Worked on the ducts on the 2nd floor in Building 'C'. Installed flue pipes in Building 'B'.
(Clegg Steel) Installed stairs on Building 'C' and delivered the beams for Building 'B'
(Utek) Finished setting Windows and doors on Building 'B' and Worked on the gable over builds.
(Reliance) Wired units on 4th floor of Building 'D' and passed inspection.
(Red Oak) Worked on gas on 3rd and 4th floors for Building 'E'. Passed inspection on 3rd and 4th floors of Building 'D'. They still do not have the flex lines to hook up the furnaces on Building 'A'.
.