Monday 1/7/2013


Weather: Partly Cloudy  16˚/-9˚ 

Subs on Site
<Wall to Wall>                  (4)
<G&M Wood>                  (6)
<Warburtons>                  (7)
<Diamond Z>                   (5)
<Extreme Fire>                (8)
<Utek>                             (11)
<Reliance>                       (4)
<Red Oak Plumbing>       (5)

Work in Progress:
(Wall to Wall) filled, caulked and primed 3 units on Building 'A'

(G&M Wood) organized the cabinets and covered them.

(Warburtons) finished the siding to the entry and patios.  Worked on Building 'C' roof and Building 'C' garage siding.

(Diamond Z) worked on the stone on the East end of Building 'A'

(Extreme Fire) worked on the plastic for Building 'E' and the attic system on Building 'C'

(Utek) finished the upper roof and chimneys on Building 'D'.  Rolled trusses on Building 'E' and rolled the 4th floor on Building 'A'

(Reliance) pulled wire on the 3rd floor of Building 'C'

(Red Oak Plumbing) showed up a noon, then took a lunch.  Worked on fire caulk on 1st floor on Building 'C'.  Water lines on 1st and 2nd floor on Building 'C' and started gas lines for 3rd and 4th floor for Building 'C'.