Thursday 1/10/2013


Weather: Partly Cloudy  29˚/12˚ 

Subs on Site
<Wall to Wall>                  (4)
<Standard Builders)         (7)
<Warburtons>                  (10)
<Diamond Z>                   (5)
<Nutek>                           (8)
<Extreme Fire>                (8)
<Utek>                             (16)
<Reliance>                       (1)
<Red Oak Plumbing>       (8)

Work in Progress:
(Wall to Wall) Painted the 4 units on the Northern end of the 1st floor of Building 'A'

(Standard Builders) Installed baseboards on the 4 Southern Units for Building 'A' 2nd Floor.  Started finish on the 4 North units on 2nd floor.  Joe discovered that the count on the doors was off.  John ordered the 2' 6" doors for the second bedroom as called out on the typical 2x2 units and not the 2' 8" doors called out on the 2x2 type 'B' units.  We [Eric (Nutek), Jesse (Utek) and Joe (Standard Builders)] got together and made a plan.  We furred in the doors to 2' 6" size in the second bed rooms on all of the units on the North half of 2nd floor and all units on 3rd & 4th floors.  Everyone seemed to work together and we are going to just get it done.  The struggle is Joe (Standard Builders) used the 2' 8" doors for the Master bedroom on these units for the 1st and 1/2 of the 2nd floors 2nd bed rooms.  John is working on getting some 2' 8" doors sent up here tomorrow or Monday, however they are special order "reinforced" doors so if he can't get them he will send standard 2' 8" doors that we can paint.  Then 4 weeks later when he can get the right doors here we can swap them.

(Warburtons) Started siding in the first of the entry gables on 4th floor and the decks on the other.  They dried in Building 'C'.

(Diamond Z) Worked on one of the entries for Building 'C'

(Nutek) sanded and swept the 4 Northern Units on 2nd floor of Building 'A',  Texured units on 3rd and 4th floors.
 Hung Building 'B' garages. Taped on the 3rd and 4th floors. 

(Extreme fire) worked on the plastic for Building 'E' and Building 'B' and the attic on Building 'C.

(Utek) rolled more trusses on Building 'E'.  Set up to the last 4 units of Building 'B' 4th floor walls.

(Reliance) finished details on the wiring 4th floor on Building 'C'


(Red Oak Plumbing) Finished water lines on 3rd floor.  Worked on the gas lines for 3rd and 4th floor of Building 'C'.  Filled the DWV for Aaron (Uintah County)  Worked on installing the tubs on Building 'D'