Monday 1/21/2013


Weather: Clear  13˚/-2˚ 

Subs on Site
<Wall to Wall>                  (4)
<SDS>                              (6)
<Cardalls>                        (5)
<Warburtons>                  (6)
<Diamond Z>                   (4)
<Extreme Fire>                (4)
<Air Doctors>                   (5)
<Utek>                             (12)
<Reliance>                       (4)
<Red Oak Plumbing>       (8)

Work in Progress:
(Wall to Wall) Primed 4 units on the North end of 2nd floor of Building 'A'

(SDS) Installed doors shelves and case on the North End of the 4th floor Building 'A'

(Cardalls) Insulated the exterior walls on 1st floor of Building 'A'

(Warburtons) Worked on the North West gable and the decks on the South East gable of Building 'A'.
(Diamond Z)Laid stone on the North West gable of Building 'C'

(Extreme Fire)Worked on the Attic system for Building 'D' and the plastic for Building 'B'

(Air Doctors) Rough in on Buildings 'D' & 'E'

(Utek) Started assembling truss sections for Building 'B'

(Reliance) Pulled wire in Building 'D' units

(Red Oak Plumbing) Stocked tubs in Building 'B' and started DWV on Building 'D'

Sub Meeting 1/14/2012

Jose (Warburtons)
Doug (Cardalls)
Eric (Nutek)
Bryson (Reliance)
William (Air Doctors)
Ether (Red Oak)
Joe (SBS)
Rob (Wall to Wall)

Talking Points:
I asked all the sub to be careful with the plastic because the labor for keeping the plastic repaired        is taking most of the day.
Hardware will be delivered on 1/28
Electrical trim will start on 1/28
Water heaters will be delivered on 1/30
Appliances will be delivered on 2/6
Diamond Z would like to scratch coat both ‘D’ & ‘E” at the same time.  When can we count on the penetrations being done on Building ‘E’- Middle of next week
Propane will be provided only for those who need it. IE Drywall tape to dry
Dumpster % breakdown was discussed and 6 of 10 subs opted to take care of their own trash. We will not provide a dumpster.
Furnaces on Building ‘A’ 1st floor are waiting for gas line material delivery.  As soon as we get gas lines hooked up Bryson (Reliance) will wire them in.

Schedule:
Building ‘A’
Handrails start Wednesday 1/23



North Tower 2nd and 3rd floor painted Thursday 1/24
Hardware starts 1/28
Electrical trim starts 1/28
Water heaters delivered 1/30



4th Floor Painted Thursday 1/31


Building ‘C’
1st floor Drops Framed starts 1/24
1st floor Ducts start 1/24
1st floor Inspection ducts and fire caulk 1/28
1st floor Drywall on hanging starts 1/29
2nd floor Insulation starts 1/22
2nd floor Pre-Rock starts 1/24
2nd floor Drops Framed starts 1/28
2nd floor Ducts start 1/29
3rd & 4th floor West tower Insulation starts 1/24
3rd & 4th floor West tower ⅝” Drywall starts 1/29

Building ‘D’
4-Way inspection Tuesday 1/29
Insulation 1st floor starts 1/30
1st Floor ⅝” drywall starts 2/4

Building ‘E’
Insulation behind the tubs and chases 1/22
Drywall behind the tubs and chases 1/23

Building ‘B’
Roof framed in 2 ½ weeks on 2/6