Friday 1/18/2013

Weather: Clear  15˚/-10˚ 

Subs on Site
<Wholesale Flooring>       (3)
<Wall to Wall>                  (4)
<Cardalls>                        (2)
<Warburtons>                  (6)
<Diamond Z>                   (4)
<Extreme Fire>                (6)
<Air Doctors>                   (6)
<Utek>                             (2)
<Reliance>                       (6)
<Red Oak Plumbing>       (8)

Work in Progress:
(Wholesale Flooring) installed the vinyl on 8 units on the South end of the 2nd and 3rd floor of  Building 'A'

(Wall to Wall) Prepped the 4 units on the Northern end of the 2nd floor of Building 'A'

(Cardalls) Insulated the exterior corridor walls on Building 'C' 1st floor.

(Warburtons) Started working on the upper sections of the North West gable and continued on the decks.

(Diamond Z) Laid stone on the North West gable of Building 'C' 

(Extreme Fire) Worked on the attic system for Building 'D'; and the plastic on Building 'B'

(Air Doctors) Rough in on Buildings 'D' & 'E'

(Utek) Details on Building 'E' draft stops for Building 'C'  attic

(Reliance) Pulled wire in Building 'D' units

(Red Oak Plumbing) Finished the gas lines on 3rd & 4th floor of Building 'D' and started DWV.

Mario and Curtis (M-13) borrowed Utek's man basket and started hanging the plastic on the gable end of Building 'C'