Wednesday 1/23/2013


Weather: Partly Cloudy  13˚/-2˚ 

Subs on Site
<Wall to Wall>                  (4)
<Nutek>                            (6)
<Cardalls>                        (5)
<Warburtons>                  (9)
<Diamond Z>                   (4)
<Extreme Fire>                (4)
<Air Doctors>                   (5)
<Utek>                             (12)
<Reliance>                       (4)
<Red Oak Plumbing>       (8)

Work in Progress:
(Wall to Wall) Primed 4 units on the North end of 3rd floor of Building 'A'.

(Nutek) Fire taped the  Pre-rock the 1st floor on Building 'C' and hung the areas around the fire sprinklers in the main rooms.

(Cardalls) Insulated 5 of the 8 units on 2nd floor Building 'C'

(Warburtons) Worked on the South West gable and finished the decks on the South East gable of Building 'A'. They started working on the area behind the 1/2 stair section so that Clegg Steel can pour the stairs on Saturday.

(Diamond Z)Laid stone on the North West gable of Building 'C'

(Extreme Fire)Worked on the Attic system for Building 'D' and the plastic for Building 'B'

(Air Doctors) Rough in on Buildings 'D' & 'E'.  Started installing the Hard ducts on the 1st floor of Building 'C'

(Utek) Assembled truss sections for Building 'B' and set the center sections

(Reliance) Pulled wire in Building 'D' units

(Red Oak Plumbing) Worked on  Water lines on Building 'D'.  Moved materials to Building 'E'.