Weather: Partly Cloudy / Hazy 22˚/7˚
Subs on Site
<Wall to Wall> (4)
<SBS> (4)
<Nutek> (3)
<Cardalls> (6)
<Warburtons> (9)
<Diamond Z> (4)
<Extreme Fire> (4)
<Air Doctors> (5)
<Nutek> (3)
<Cardalls> (6)
<Warburtons> (9)
<Diamond Z> (4)
<Extreme Fire> (4)
<Air Doctors> (5)
<Utek> (12)
<Reliance> (4)
<Red Oak Plumbing> (8)
Work in Progress:
(Wall to Wall) Painted 4 units on the North end of 3rd floor of Building 'A'.
(SBS) Laid base board on the Southern 4 units of the 4th floor of Building 'A'
(Cardalls) Insulated the rest of 2nd floor Building 'C'. Started the West end of 3rd floor Building 'C'
(Warburtons) Worked on the South West gable of Building 'A'. They finished working on the area behind the 1/2 stair section so that Clegg Steel can pour the stairs on Friday. Started drying in Building 'E'. They continue to have trouble with starting their man basket in the mornings.
(Diamond Z)Laid stone on the North East gable of Building 'C'
(Extreme Fire)Worked on the Attic system for Building 'D' and the plastic for Building 'B' and installed trim on 1st and 2nd floor of Building 'A'
(Air Doctors) Rough in on Buildings 'D' & 'E'. Finished installing the Hard ducts on the 1st floor of Building 'C'
(Utek) Assembled truss sections for Building 'B' and set the rest of the main sections
(Reliance) Pulled wire in Building 'D' units
(Red Oak Plumbing) Finished water lines on Building 'D'. Started Fire caulk. Moved materials to Building 'E'.
Clegg Steel called me earlier in the week to ask if they could pour the stair pans on Saturday 1/26. They called today and told me that they had to pour on Friday 1/25. The finish carpenters will finish tonight and I moved the floor layers from Friday to Monday because they would not have access.
Clegg Steel called me earlier in the week to ask if they could pour the stair pans on Saturday 1/26. They called today and told me that they had to pour on Friday 1/25. The finish carpenters will finish tonight and I moved the floor layers from Friday to Monday because they would not have access.