Weather: Clear 16˚/-9˚
Subs on Site
<Wall to Wall> (4)
<Nutek> (6)
<Cardalls> (5)
<Warburtons> (9)
<Diamond Z> (4)
<Extreme Fire> (4)
<Air Doctors> (5)
<Cardalls> (5)
<Warburtons> (9)
<Diamond Z> (4)
<Extreme Fire> (4)
<Air Doctors> (5)
<Utek> (12)
<Reliance> (6)
<Red Oak Plumbing> (8)
Work in Progress:
(Wall to Wall) Painted 4 units on the North end of 2nd floor of Building 'A'
(Cardalls) Insulated the exterior walls on 1st floor of Building 'C' and started on 2nd floor
(Warburtons) Worked on the North West gable and the decks on the South East gable of Building 'A'.
(Diamond Z)Laid stone on the North West gable of Building 'C'
(Extreme Fire)Worked on the Attic system for Building 'D' and the plastic for Building 'B'
(Air Doctors) Rough in on Buildings 'D' & 'E'
(Utek) Started assembling truss sections for Building 'B'
(Reliance) Pulled wire in Building 'D' units