Wednesday 1/9/2013


Weather: Partly Cloudy  23˚/-7˚ 

Subs on Site
<Wall to Wall>                  (4)
<Standard Builders)         (7)
<Warburtons>                  (9)
<Diamond Z>                   (5)
<Nutek>                           (8)
<Extreme Fire>                (8)
<Utek>                             (16)
<Reliance>                       (4)
<Red Oak Plumbing>       (5)

Work in Progress:
(Wall to Wall) Primed the 4 units on the Northern end of the 1st floor of Building 'A'

(Standard Builders) Installed finish on the 4 Southern Units for Building 'A' 2nd Floor.

(Warburtons) Started siding in the first of the entry gables on 4th floor and the decks on the other.  Craig and Rick came on site and loaded a dump trailer full of trash then left the trailer for more.

(Diamond Z) worked on the stone for the East end of Building 'A'.  Then started on one of the entries.

(Nutek)Textured the 4 Northern Units on 2nd floor of Building 'A', Hung Building 'B' garages.

(Extreme fire) worked on the plastic for Building 'E' and Building 'B' and started the attic on Building 'C.

(Utek) rolled more trusses on Building 'E'.  Set up to the center of Building 'B' 4th floor walls.

(Reliance) finished wiring 4th floor on Building 'C'

(Red Oak Plumbing) Finished water lines on 2nd floor and started on 3rd floor.  Worked on the gas lines for 3rd and 4th floor of Building 'C'.  Worked on installing the tubs on Building 'D'

The power lines supplying the temp power for the site burnt off the transformer in the night.  We arrived to no heat in the trailers and the lifts block heater did not work.