Weather: Clear 3˚/-13˚
Subs on Site
<Wall to Wall> (4)
<Cardalls> (4)
<Warburtons> (6)
<Diamond Z> (4)
<Nutek> (8)
<Extreme Fire> (6)
<Air Doctors> (6)
<Utek> (12)
<Reliance> (6)
<Red Oak Plumbing> (8)
Work in Progress:
(Wall to Wall) Primed the 4 units on the Southern end of the 3rd floor of Building 'A'
(Cardalls) Box Truck would not start at the hotel. I went and picked them up. At lunch I took Doug to get some #1 diesel to add to their fuel so that it would not gel. They blew in the insulation for Building 'A'
(Warburtons) worked on the North East entry and decks of Building 'A'. Worked the North West decks.
(Diamond Z) Laid stone on the North West corner of Building 'C'
(Nutek)Touched up the last 4 units on 4th floor of Building 'A' taped behind the tubs on 2nd and 3rd floors in Building 'D' and hung the drywall on the chase ceilings for Building 'E'
(Extreme Fire) Attic system on Building 'C' Plastic system in Building 'B'
(Utek) Finished the rest of the roof on Building 'E'. Worked on the exterior parts of Building 'B'.
(Reliance) Started pulling wire on Building 'D'
(Red Oak Plumbing) Worked on the gas lines for the 1st and 2nd floors of Building 'D' and set the tubs on 2nd and 3rd floor.of Building 'D'. I walked Building 'C' and made a list of fire caulk items that still needed to be done. I gave them the list at 9 am and told them we had inspection at 1 pm. They failed again. Re inspection on Friday.