Wednesday 1/30/2013


Weather: Partly Cloudy  25˚/6˚ 

Subs on Site
<G & M>                           (5)
<Wall to Wall>                  (4)
<SBS>                              (1)
<Nutek>                            (10)
<Cardalls>                        (4)
<Warburtons>                  (8)
<Air Doctors>                   (4)
<Utek>                             (12)
<Reliance>                       (4)
<Red Oak Plumbing>       (6)

Work in Progress:
(G & M) Installed cabinets on the North end of 2nd and 3rd floor in Building 'A'.

(Wall to Wall) Primed 4 units on the South end of the 4th floor of Building 'A'.

(SDS) Hung the Breeze way doors on 3rd and 4th in Building 'C'

(Nutek) Finished hanging pre-rock on the East end of 3rd and 4th floor in Building 'C'  Fire taped 3rd floor Building 'C'.   Taped behind the tubs on Building 'E'.  LKL delivered the sheetrock for Building 'D' and stacked it for speedy stocking in the Building tomorrow.  They brought out a regular shop forklift which got stuck.  They borrowed our lift and said they would top off the gas when they are finished.

(Cardalls) Installed insulation on the East units on 4th floor of Building 'C'.  Started insulation on Building 'D' 1st floor.

(Warburtons) Worked on the South East gable of Building 'A'. Installed siding on the South center section of  Building 'C' 

(Air Doctors) Worked on the ducts on the 2nd floor in Building 'C' then started on the West end of 3rd floor. Installed flue pipes in Building 'B'. 

(Utek) Set Windows and doors on Building 'B' and Worked on the gable over builds.

(Reliance) Wired units on 4th floor of Building 'D'

(Red Oak)Worked on gas for Building 'E'. The filled the DWV in Building 'D'.  Rob (Red Oak) did not turn the fire hydrant all of the way on and water came up from the ground and down the road.  They passed Building 'D' re-inspections.





We had a robbery last night.  I got a call from the Sheriff this morning.  Apparently, I guy named Powell and a female came here looking for a door for a buddy.  We do not have any on site that are not hung so they stole some cordless tools and while trying to leave they got high centered on a curb between the garages.  The Sheriff impounded their vehicle and could not find Powell.  They brought in a K9 and found him in Building 'B' or 'E' (The Sheriff just knew it had no heat).  Powell confessed and the tools are in his vehicle in the impound lot.  The Sheriff said it might take unit tomorrow to get the warrant to get tools out of the vehicle. 

Air Doctors did get their tools back, estimated $1000 worth.  Unit 201 in Building 'C' had the insulation pulled out of the walls and the plastic was shredded.  They might have found him in that unit.  I went to the Sheriff Station and asked for the report for our records.  Because they caught the guy it is now a prosecution and we will have to wait at least a week before we can get the report from the County Attorney.