Weather: Partly Cloudy 23˚/-7˚
Subs on Site
<Wall to Wall> (4)
<Standard Builders> (7)
<Warburtons> (7)
<Diamond Z> (5)
<Nutek> (9)
<Extreme Fire> (10)
<Utek> (16)
<Reliance> (4)
<Red Oak Plumbing> (5)
Work in Progress:
(Wall to Wall) Painted the 4 units on the Southern end of the 1st floor of Building 'A'
Subs on Site
<Wall to Wall> (4)
<Standard Builders> (7)
<Warburtons> (7)
<Diamond Z> (5)
<Nutek> (9)
<Extreme Fire> (10)
<Utek> (16)
<Reliance> (4)
<Red Oak Plumbing> (5)
Work in Progress:
(Wall to Wall) Painted the 4 units on the Southern end of the 1st floor of Building 'A'
(Standard Builders) Installed finish work on 2 units on the North end of 3rd floor in Building 'A'
(Warburtons) installed house wrap in the first of the entry gables on 4th floor.
(Diamond Z) worked on the stone for the East end of Building 'A'
(Nutek) Taped on the 3rd and 2nd Floor Building 'A' and hung the decks and breezeways on the 4th floor of Building 'A'
(Extreme fire) worked on the plastic for Building 'E' and Building 'B' and started the attic on Building 'C'. They also followed the inspector installing draft stops in the attic for Building 'A'
(Utek) installed the framed columns in the North entries to Building 'C'. Finished the last details on Building 'D' roof. Rolled more trusses on Building 'E'. Finished sheeting the South end of Building 'B' 4th floor. Stood the 1st 2 units on Building 'B' 4th floor.
(Reliance) Pulled wire on 3rd floor Building 'C'
(Red Oak Plumbing) passed inspection for 1st and 2nd floor on Building 'C' gas lines. Finished 4 units of water line on 2nd floor of Building 'C'. Stocked tubs in Building 'D'.