Tuesday 1/29/2013


Weather: Snow 25˚/-4˚ 

Subs on Site
<Wall to Wall>                  (4)
<SBS>                              (1)
<Nutek>                            (10)
<Cardalls>                        (4)
<Warburtons>                  (8)
<Air Doctors>                   (4)
<Utek>                             (12)
<Reliance>                       (4)
<Red Oak Plumbing>       (6)

Work in Progress:
(Wall to Wall) Primed 4 units on the North end of the 4th floor of Building 'A'.

(SDS) Came back to install trim on the attic accesses in Building 'A' as well as fix some trim that was cut too short.

(Nutek)n Finished hanging pre-rock on the West end of 3rd floor in Building 'C' Started the 4th floor. Fire taped the last 4 units on 2nd floor Building 'C'. Hung the lids in Building 'B' chases.  Taped behind the tubs on Building 'E'

(Cardalls) Installed insulation on the West units on 4th floor of Building 'C'.and started on the East side on 3rd floor.

(Warburtons) Worked on the South East gable of Building 'A'. Installed siding on the South East corner of  Building 'C' 

(Air Doctors) Worked on the ducts on the 2nd floor in Building 'C'. Installed flue pipes in Building 'B' 

(Utek) Set Windows and doors on Building 'B' and cleaned off the snow of the roof so they could work on the over builds from the gables... 

(Reliance) Wired units on 3rd floor of Building 'D'

(Red Oak) Started drilling out Building 'E' and running gas lines. Water Heaters were delivered and they stocked Building 'A' with them. Failed 4-way but took the list and finished it up for tomorrows inspection.