Weather: Clear 10˚/-10˚
Subs on Site
<Wall to Wall> (4)
<Cardalls> (2)
<Warburtons> (6)
<Diamond Z> (4)
<Nutek> (3)
<Extreme Fire> (6)
<Air Doctors> (6)
<Utek> (8)
<Reliance> (6)
<Red Oak Plumbing> (8)
Work in Progress:
(Wall to Wall) Painted the 4 units on the Southern end of the 3rd floor of Building 'A'
(Cardalls) Box Truck would not start at the hotel. I went and picked them up. They finished the ceilings and party walls on the 1st floor Building 'C'. Corey Coleman (IECC) inspected.
(Warburtons) Finished on the North East entry and decks of Building 'A'. Worked the North West decks. I spoke to them about clean-up and not leaning any boards on the textured or painted walls in the units.
(Diamond Z) Laid stone on the North West corner of Building 'C'
(Nutek) Taped behind the tubs on 4th floor in Building 'D' and hung the drywall on the corridor ceilings for Building 'C' North end.
(Extreme Fire) Attic system on Building 'D' Plastic system in Building 'B'. They are waiting on the heads for Building 'C' Attic system.
(Utek) Worked on the lower entry gables on Building 'E'.
(Reliance) Continued pulling wire on Building 'D'
(Red Oak Plumbing) Worked on the gas lines for the 3rd and 4th floors of Building 'D' and set the tubs on 2nd and 4th floor.of Building 'D'. Passed inspection on the gas lines for the 1st and 2nd floors on Building 'D'