Subs on Site
<Wall to Wall> (4)
<Standard Builders> (6)
<Cardalls> (2)
<Warburtons> (4)
<Diamond Z> (4)
<Nutek> (8)
<Extreme Fire> (4)
<Air Doctors> (6)
<Utek> (12)
<Reliance> (6)
<Red Oak Plumbing> (8)
Work in Progress:
(Wall to Wall) Painted the 4 units on the Southern end of the 2nd floor of Building 'A'
(Standard Builders) Finish work on the 3rd floor of Building 'A'
(Cardalls) Box Truck would not start at the hotel. I went to jump start them and it still would not start. I bought some starting fluid and fuel treatment and it would still not start. We loaded their tools into my truck and I gave them I ride to work. Then I gave one of them a ride out in the afternoon when it was warmer and it would not start. Doug (Cardalls) bought jumper cables and a magnet heater for the engine. I let them take a propane heater to warm it when I gave them a ride home last night. They got it running by 10 pm. They had a delivery truck come. The driver locked his keys in the truck then drove over the curb and got the truck stuck.
(Warburtons) worked on the North East entry and decks of Building 'A'. Started the North West decks.
(Diamond Z) Laid stone on the South West corner of Building 'C'
(Nutek) Taped units on 4th floor of Building 'A'. Hung drywall behind the tubs and chases in Building 'D' and taped the 1st floor. They also went through Building 'A' and installed drywall and Bull nose corner bead on each pony wall.
(Extreme Fire) Attic system on Building 'C' Plastic system in Building 'B'
(Utek) Finished the main section of the roof on Building 'E'. Worked on the exterior parts of Building 'B'. Willard Sr. Hit the transformer on the North end of Building 'B' with their fork lift.
(Reliance) Started setting interior panels on Building 'D'
(Red Oak Plumbing) Worked on the gas lines for the 1st and 2nd floors of Building 'D' and set the tubs on 1st floor.