Thursday 1/3/2013

Weather: Partly Cloudy  10˚/-11˚ 

Subs on Site
<Standard Builders>        (6)
<Warburtons>                  (3)
<Diamond Z>                   (5)
<Extreme Fire>                (8)
<Utek>                             (14)
<Reliance>                       (5)
<Red Oak Plumbing>       (5)

Work in Progress:
(Standard Builders) Started finish South end of 1st floor on Building 'A'.  

(Warburtons) Worked on the roof for Building 'C', siding on Building 'C' garage.

(Diamond Z) Started stone on the West end of Building 'C'

(Extreme Fire) Worked on the attic system for Building 'C' and the plastic on Building 'D'

(Utek) finished the entry gables on Building 'C'.  Stood walls on 7 of the 8 units for Building 'B' 3rd floor. and prepped to set the 4th floor floor sections.

(Reliance) wired the last unit on 2nd floor and started on 3rd in Building 'C'.

(Red Oak Plumbing) ran the gas lines on the East end of 1st and 2nd floor on Building 'C'.  Ran water lines and worked on fire caulk on 1st and 2nd floor Building 'C'

I was told today by Konrad (Nutek) that we may have people sleeping in Building 'A' at night possibly only on the weekends.  I am going to call the County Sheriff this weekend and have him take a look.