Wednesday 1/2/2013

Weather: Partly Cloudy  6˚/-13˚ 

Subs on Site
<Standard Builders>        (6)
<Warburtons>                (3)
<Diamond Z>                  (5)
<Extreme Fire>               (8)
<Utek>                            (14)
<Reliance>                      (5)
<Red Oak Plumbing>       (5)

Work in Progress:

(Standard Builders) Stocked material and doors to get ready for the South end on Building 'A'.  Set up their tools on the 1st floor.

(Warburtons) Worked on the roof for Building 'C', siding on Building 'C' garage.

(Diamond Z) Started stone on the West end of Building 'C'

(Extreme Fire) Worked on the attic system for Building 'C' and the plastic on Building 'D'

(Utek) framed the entry gables on the North side of Building 'C'.  Sheeted the South end of 3rd floor Building 'B'.  Stood wall section for Building 'B' 3nd floor.

(Reliance) Wired 1st and 2nd floor Building 'C'

The Fuel in the lift gel-ed.  The fuel in Diamond Z's heater gel-ed.  There was mud frozen in the units with heaters running.  The drywall in one of the units on Building 'A' 4th floor had condensation on it.