Weather: Partly Cloudy / Hazy 29˚/8˚
Subs on Site
<Wall to Wall> (4)
<Nutek> (3)
<Cardalls> (6)
<Warburtons> (7)
<Diamond Z> (4)
<Clegg Steel> (8)
<Air Doctors> (5)
<Cardalls> (6)
<Warburtons> (7)
<Diamond Z> (4)
<Clegg Steel> (8)
<Air Doctors> (5)
<Utek> (12)
<Reliance> (2)
<Red Oak Plumbing> (2)
Work in Progress:
(Wall to Wall) Cleaned and stripped 4 units on the North end of 3rd floor of Building 'A'.
(Nutek) Hung pre-rock on Building 'C' 2nd floor units.
(Warburtons) Worked on the South West gable of Building 'A' and started on Building 'C'
(Diamond Z) Finished all they could on Building 'C' until the roofers finish the flashing.
(Clegg Steel) Poured the stairs on Building 'A'
(Air Doctors) Worked on the ducts on the first floor in Building 'C'
(Utek) Started sheeting the roof on Building 'B' and built the hip on the North end.
(Reliance) Wired units on 3rd floor of Building 'D'
(Red Oak) Worked on Fire Caulk for Building 'D'