
Subs on Site
<Air Doctors> (3)
<Sterns> (12)
<Red Oak Plumbing> (5)
<Red Oak> (6)
<DG Concrete> (2)
Work in Progress:

(Sterns) poured the radius' and augured the areas were they will slip tomorrow on the East side.
(Red Oak Plumbing) prepped and passed inspection on Building 'E' underground. Then back filled.
(Red Oak) got ready for a pour on Building 'B' garage walls but we do not have straps nor a framer to supply them, so they poured Building 'A' Garage floor. They started forming the Club House footings. Th
(DG Concrete) worked with Sterns to install the roof drain pipes were possible and continued with parking sub grade.